Task (taken from Action Plan)
|
|
|
|
|
Progress to date / Reason for any delays
|
|
|
|
|
|
|
|
|
|
|
Prepare schedule of all leased and licensed open spaces
including play areas
|
|
David Wilson/Legal/George Douglas
|
|
|
|
Schedule in place with basic information by Jan 02.
Delay due to staff shortages and other higher priorities.
|
Further work: Sites to be captured on GIS and data linked.
By end March 03.A fundamental review of the Council's whole asset
data base now underway due for completion end 02
|
|
|
|
-identify leaseholders/licensee holders
|
|
David Wilson/Legal/George Douglas
|
|
|
|
|
|
-identify renewal/review dates and review a bring forward
system
|
|
David Wilson/Legal/ George Douglas
|
|
|
|
|
|
-identify renewal/review dates and review a bring forward
system
|
|
David Wilson/Legal/George Douglas
|
|
|
|
|
|
Develop a policy for leased and licensed open spaces
ownership and management
|
|
Gill Gowing/Kevan Lavender
|
|
|
|
Delay due to other priorities and lack of
resources/expertise in this area. Now that an
appropriately-qualified member of staff (Estates Officer) has been
appointed, this work can be undertaken. Additional action arising
from CROW Act identified in respect of Commons.
|
|
|
|
|
|
|
|
|
|
|
Undertake risk assessment next time a grave is
dug
|
|
|
|
|
|
|
|
Undertake a risk assessment of the cemetery and its
monuments
|
|
|
|
|
Physical risk assessment undertaken.
|
|
|
|
Appoint a preferred operative to dig graves and approve
working practices
|
|
|
|
|
Was not until Dec that a grave was dug and risk assessment
could be made and approval be given.
|
|
|
|
Advise undertakers that they must use the preferred
contractor or an alternative contractor subject to their submitting
a method statement and complying with
|
Health and Safety requirements
|
|
|
|
|
In practice only a single contractor used. The method
statement of this contractor has been agreed and will be used if
another contractor is used.
|
|
|
|