Phase 6 - Cressex Road / Cressex Link Road Junction Improvements and Proposed Cycleway (Decision taken)

Decision Maker: Leader of the Council

Decision status: Recommendations approved

Is Key decision?: Yes

Purpose:

Phase 6 - Cressex Road / Cressex Link Road Junction Improvements and Proposed Cycleway along Cressex Road. The Public Consultation is from the 02nd March until the 06th April 2018.

Decision:

The Leader of the Council:

 

AGREED: To support the final designs including amendments made during consultation of Phase 6 so that the project can begin construction in Autumn 2018. Post consultation designs are provided in Appendix 1 as a pdf.

 

AGREED: To support the decision not to implement any cycling facilities in line with public feedback following consultation.

 

AGREED: To delegate authority to the Head of Highways Infrastructure Projects for any further design changes in consultation with the Cabinet Member for Transportation and Local Member.

 

AGREED: To agree to support the procurement of a main works contractor in line with the agreed budgets as defined within T12.16 - High Wycombe Town Centre Master Plan Southern Quadrant HWTCMPSQ Business Case.

 

AGREED: To delegate authority to the Head of Highways Infrastructure Projects to approve the award of the construction contract in line with the High Wycombe Town Centre Business Case in consultation with the Cabinet Member for Transportation.

 

Publication date: 15/06/2018

Date of decision: 15/06/2018

Effective from: 21/06/2018