Decision details
Decision Maker: Leader
Decision status: Recommendations approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To agree the procurement options for
delivering the Aylesbury Electricity Grid HIF project
Decision:
Recommendations:
To NOTE that the Non-Contestable Works can only be delivered by UK Power Networks, due to their regulated role in the local network, noting also the exemption for such works from Public Contracting Regulations.
To AGREE for the Contestable Works and Adoption Agreement to be subject to a competitive tendering process. Contract award will be subject to a separate key decision subject to costs remaining within the allocated grant funding
Contact: Edward Barlow, Head of Energy & Resources Email: Edward.Barlow@buckinghamshire.gov.uk.
Publication date: 11/03/2021
Date of decision: 19/03/2021
Accompanying Documents: