Purpose:

To agree the procurement options for delivering the Aylesbury Electricity Grid HIF project

Decision:

The Leader:

 

NOTED that the Non-Contestable Works can only be delivered by UK Power Networks, due to their regulated role in the local network, noting also the exemption for such works from Public Contracting Regulations.

 

AGREED for the Contestable Works and Adoption Agreement to be subject to a competitive tendering process. Contract award will be subject to a separate key decision subject to costs remaining within the allocated grant funding

Contact: Edward Barlow, Head of Energy & Resources Email: Edward.Barlow@buckinghamshire.gov.uk.

Publication date: 19/03/2021

Date of decision: 19/03/2021

Effective from: 25/03/2021