Purpose:

Decision upon progressing the Aylesbury Grid Reinforcement Project to bring forward additional electricity supply to the south west of Aylesbury Garden Town. The project uses grant funding from the (Homes England) Housing Infrastructure Fund.

Decision:

The Deputy Leader and Cabinet Member for Planning and Regeneration, on behalf of the Leader:

 

AGREED to accept “Option A” from connection offer 8600022871 for 31MVA provided by UK Power Networks (UKPN). 

 

 

This decision is being taken under the ‘special urgency’ provisions of the constitution due to the deadline of the connection offer from UK Power Networks which does not allow time for the usual decision-making timescales

Wards Affected: Aylesbury South East; Bernwood; Ridgeway East; Stone & Waddesdon; The Risboroughs; Wendover, Halton & Stoke Mandeville;

Contact: David Johnson, Energy & Climate Project Officer Email: David.Johnson@buckinghamshire.gov.uk.

Publication date: 20/10/2021

Date of decision: 20/10/2021