HS2 Ltd has submitted a Schedule 4 (highways
approval) under HS2 Hybrid Act 2017 to the Council to construct a
roundabout at Keeper's Lane to facilitate access to the vent shaft
at Little Missenden. The solution identified in the HS2 submission
has raised concerns locally which HS2 Ltd is aware of. A decision
needs to be made less than 28 days after submission otherwise the
approval deems.
Decision type: Key
Decision status: Recommendations Approved
Wards affected: Chiltern Ridges; Great Missenden;
Notice of proposed decision first published: 23/12/2020
Decision due: 28 Jan 2021 by Deputy Leader and Cabinet Member Transport, Leader
TR01.21
Lead member: Councillor Nick Naylor Nick.Naylor@buckinghamshire.gov.uk
Contact: Joan Hancox, Head of Transport Strategy Email: joan.hancox@buckinghamshire.gov.uk.
Decisions
- 20/01/2021 - Little Missenden Vent Shaft access Schedule 4 (Decision to be taken)
- 28/01/2021 - Little Missenden Vent Shaft access Schedule 4