BUDGETARY CONTROL REPORT TO 30 JUNE 2004 |
The tables below report the budgetary control positions for the General Fund and the Capital Programme for the first 3 months of the financial year 2004/2005. |
A bracketed figure () is a negative figure. It is used to identify either income or a variance that leaves the Authority in a worse financial position, such as over spending or lower collection of income. A non-bracketed figure is positive and will either represent expenditure or a variance that leaves the Authority in a better financial position, such as underspending or additional income generation. |
GENERAL FUND POSITION |
Set out below is the General Fund position as at the end of June 2004. These figures exclude any under/overspending on Business Units. At the end of June there is a total net underspend of £2,598,000 compared to the profiled budget. This is represented by delayed expenditure of £1,687,000 and misprofiled budgets of £450,000 leaving a surplus of £461,000. However, there is also a net overspend on Business Units of £436,000 which reduce this surplus to £25,000. |
|
|
|
|
|
|
General Fund Totals By Cabinet Member |
|
|
Commentary on Major Variances |
The above table is presented in line with the portfolio structure. All of the figures included in this report have been presented to budget holders and where appropriate issues have been highlighted to and actions identified. These will be monitored and reported on to Strategic Directors Board where appropriate. |
A brief explanation of the significant variances is provided in the commentary section below. |
|
|
CAPITAL PROGRAMME |
The schemes contained in the Capital Programme have been divided into two distinct areas: |
|
|
The table below presents by Directorate the current position for operational schemes for the first three months of the year. |
Capital Programme Summary 2004 - 2005 |
|
|
Commentary on Operational Schemes |
There are currently 38 operational schemes and 34 funded – Protected schemes. The reported overspends against Corporate Resources and Customer Services are due to budget phasing differences and project officers have been requested to supply updates to the current budget phasings. Within Community & Housing the Lane End Community Centre has outstanding brought forward Creditor provisions of £37,400 and within Planning Directorate the H W Town Centre Development Scheme has £791,632 outstanding Creditor provisions relating to CPO’s committed but not yet paid. The budget balance remaining on Operational schemes is £10.7 million. |
|