Meeting documents
|
|
|
|
In accordance with the previously published schedule and reports, the officer has taken the following key decision: |
The decision will take effect on Tuesday 10 June 2003. |
Title |
The selection of contractor for the construction of Lane End Youth and Community Centre. |
|
Reference Number |
Schedule 45 - 57/2003 |
|
Decision Taken |
To appoint Contractor 1 to construct the Lane End Youth and Community Centre. |
|
Date of Publication |
Monday 2 June 2003 |
|
Reasons for Decision |
Contractor 1 has submitted the lowest tender and had advised that the contract can be completed within the specified 22-week period. |
|
Consultation Undertaken |
Prepared in consultation with the Community Portfolio holder Cllr Mrs Julia Langley who is in agreement with the proposed decision. |
|
Your Questions and Views |
If you have any views on this decision that you would like the officer to consider or if you wish to object to the decision taken, please inform Barbara Maher. This can be done by telephone (01494) 421240 or e-mail barbara_maher@wycombe.gov.uk. |
|
|
|