Schedule No: 3

Published:  10 June 2002

 

 

Part 1

Proposed Decisions within Cabinet Portfolios

Page Nos

 

These decisions are proposed to be taken after (publication date + 3 days).  Any comments should be made to the Cabinet Member indicated in the Schedule by that date.

 

 

None

 

 

 

Part 2

Decisions taken within Cabinet Portfolios

Page Nos

 

These decisions will be implemented after (publication date + 5 working days) unless ‘called-in’ for further consideration.

 

 

None

 

 

 

Part 3

Key Decisions taken by Officers
Under Delegated Powers

Page Nos

 

These decisions will be implemented after (publication date + 5 working days) unless ‘called-in’ for further consideration.

 

 

 

To award the contract for the works to Coates Fencing Ltd. based on the tender submission of £160,973.50 and to release the full capital allocation of £225,000 to meet the cost of the contract including contingencies and additional fencing at properties not yet included in the contract.

1

 

 

Part 4

Urgent Decisions Taken

Page Nos

 

These decisions require urgent action and have been implemented.  They may be ‘called-in’ for post-implementation review.

 

 

That the Housing Term Maintenance Contract between this Council and Mears Building Contractors Limited is extended to 22 July 2002, under the existing contract terms and conditions.

2

 

 

Part 5

Executive Decisions Called-In from Last Schedule

Page Nos

 

Appointments to the Chilterns AONB Strategy Panel.
 

3

 

INSPECTION OF REPORTS AND
BACKGROUND PAPERS

 

This Schedule and reports relating to proposed decisions and decisions taken (other than those which contain exempt or confidential or other excepted information are deposited for public inspection at:

·

Reception, Queen Victoria Road Offices

·

Marlow Area Information Centre

Risborough Area Information Centre

·

The Council’s Website at www.wycombe.gov.uk

Background Papers can be inspected by contacting the officer named under each decision or proposed decision.

General enquiries about this schedule should be made to:- the Council Secretariat 01494 421214

 

 

 

This Schedule is issued by the Head of Corporate and Committee Administration, Council Offices, Queen Victoria Road, High Wycombe Bucks, HP11 1BB.

 

 

Part 3 - Key Decisions Taken by Officers Under Delegated Powers

 

 

Officer: Ian Westgate    

Tel:  01494 421401    

Fax: ………………01494 421464…………………………………………..

Email: ian_westgate@wycombe.gov.uk    

Relevant Improvement & Scrutiny Committee: Social

Decision Number

Decision Taken

Date Taken

 

(Title of Report):  Award of Contract, Castlefield Environmental Improvements. Installation of gates, railings and fencing to council properties.

Ward(s) affected: Castlefield and Booker

Decision:

To award the contract for the works to Coates Fencing Ltd. based on the tender submission of £160,973.50 and to release the full capital allocation of £225,000 to meet the cost of the contract including contingencies and additional fencing at properties not yet included in the contract.

Reason for Decision

This was the only priced tender received and is within budget provision.

Consultation Undertaken:

The consultation included a Planning for Real event, which was held in the local school in 1999. The event demonstrated that residents considered the improvement of the service road environment to be critical to the reduction of crime and the improvement of local living conditions. There has been ongoing liaison with the community, particularly through the Castlefield Challenge Partnership. Ward Members have also been involved throughout the project.

Each council tenant within the project area has been consulted and offered a choice of fencing type to suit their particular preferences.

Officer Contact:

Ollie Kelly 01494 421816 or email: ollie_kelly@wycombe.gov.uk

 

 

 

 

Part 4 – Urgent Decisions Taken

 

 

Portfolio: Housing    

Cabinet Member: Cllr Mrs P Priestley…………………………………...

Tel: 01844 275308……………………………………………………………

Fax: as above…………………………………………………………..

Email: cllr_priestley@hotmail.com………………………………………………………..

Relevant Improvement & Scrutiny Committee:

Decision Number

Decision Taken

Date Taken

 

(Title of Report):  Housing Term Maintenance Contract

Ward(s) affected: All

Reason for Urgency:

To ensure continuity of service and compliance with the Best Value Improvement Plan for Housing Repairs and Maintenance.

Decision:

That the Housing Term Maintenance Contract between this Council and Mears Building Contractors Ltd. is extended to 22 July 2002, under the existing contract terms and conditions.

Reason for Decision:

See reason for urgency.

Consultation Undertaken:

With the Cabinet Member for Housing and the Chairman of the Council.

Urgency procedures approved by the following Improvement & Scrutiny Chairman (or Chairman of the Council in his/her absence):

Approved by the Chairman of the Council
 

 

Officer Contact:

Richard Smith 01494 421503 or email: richard_smith@wycombe.gov.uk

 

 

 

 

Part 5 – Cabinet Decisions called-in from the Last Schedule

 

 

Portfolio: Leader    

Cabinet Member:  Cllr R B Colomb       

Tel: 01494 815004    

Fax: ………………as above…………………………………………..

Email …………roger_colomb@wycombe.gov.uk………………………………………………

Decision Number

Decision Called-In

Called In
By

How/When
to be reconsidered

1/2002

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Appointments to the Chilterns AONB Strategy Panel.

Cllrs D A Anson, J M Blanksby, J M Campbell, Miss S E Marshall and Mrs A M Stenner with the agreement of Cllr N P Vickery, Chairman of the Environment I & S Committee.