Decision details

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Update on the SEALR project

Decision:

Cabinet received a report on the South East Aylesbury Link Road (SEALR) project which was the construction of approximately 1.1 miles of dual carriageway including 3 new roundabout junctions. The report related to SEALR Phase 2, between B442 Lower Road and the Stoke Mandeville Relief Road being constructed by HS2.

 

The Stoke Mandeville Relief Road was mitigation identified through the HS2 Act, arising from the closure of the A4010. The A4010 was the main route between Aylesbury and Princes Risborough and was a blue light route. The Council had previously entered into a funding and delivery agreement with HS2 for the SEALR phase 2 project, which enabled the Council to replace a section of the single carriageway Stoke Mandeville Relief Road with a dual carriageway road and a new roundabout providing access to the future South West Aylesbury Link Road.

 

The funding agreement was the contractual mechanism whereby HS2 provided partial funding, based on the cost of delivering the single carriageway Stoke Mandeville Relief Road, in return for the Council delivering SEALR Phase 2, within a specified time period. The report sought the necessary delegations to deliver SEALR Phase 2, within the required timeframes to achieve the intended programme and meet its contractual obligations with HS2.

 

RESOLVED –  

 

  1. To amend the Cabinet delegation in December 2022, and delegate authority to the Corporate Directors of Communities and of Planning Growth and Sustainability, in consultation with the Leader of the Council, to:  
  1. Proceed with the delivery of Phase 2 of the South East Aylesbury Link Road. 
  1. Take all necessary steps including to enter into any associated agreements, contracts or licenses required associated with the delivery and funding of the works in relation to (i) above. 

 

  1. That it be AGREED to approve and release an increase to the budget in the Capital Programme for SEALR Phase 2 as set out in the confidential Appendix B, funded from reapportioned HIF grant subject to Homes England approval, HS2 Funding Agreement and Section 106 contributions. 

Wards Affected: Aston Clinton & Bierton; Aylesbury South East; Wendover, Halton & Stoke Mandeville;

Details of any conflict of interest declared: None

Contact: Richard Barker, Corporate Director Communities Email: Richard.Barker@buckinghamshire.gov.uk.

Report author: Kevin Goad

Publication date: 04/01/2024

Date of decision: 04/01/2024

Decided at meeting: 04/01/2024 - Cabinet

Effective from: 12/01/2024