Decision details
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To proceed with the implementation of raised
crossings/ speed humps at Pershore Way, Valor Drive and Avalon
Street, Aylesbury.
Reasons for the decision:
In July 2020, planning permission was received
by Buckinghamshire Council for the implementation of the Haydon
Hill cycleway scheme.
Construction of the cycleway started on Monday 19th April 2021 (for
a period of 4 months).
We are now working on proposals for implementing the raised
crossing points/ speed humps at Pershore Way and Valor Drive. This
will allow for smooth transition of pedestrians and cyclists. A
Notice about the proposals was put on site and in the press on 28th
July 2021 for a period of 21 days. Other key stakeholders were
consulted on. Deadline of consultation is 18th August 2021.
Alternative options considered:
Do nothing - will not provide smooth
transition of pedestrians and cyclists at Pershore Way and Valor
Drive
Wards Affected: Aylesbury North West; Stone & Waddesdon;
Details of any conflict of interest declared: N/A
Contact: Ian McGowan, Head of Highways Infrastructure Projects Email: Ian.McGowan@buckinghamshire.gov.uk.
Publication date: 18/08/2021
Date of decision: 19/08/2021
Accompanying Documents: