Decision details

Decision Maker: Deputy Leader and Cabinet Member Transport, Leader

Decision status: Recommendations approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Upgrading Emerald Way cycle route along Rabans Lane, through Fairford Leys and into the Town Centre

Decision:

The Leader:

 

NOTED the results of the public consultation.

 

AGREED to delegate authority to the Head of Highways Infrastructure Projects to complete detailed design following public feedback.

 

AGREED to delegate authority to the Head of Highways Infrastructure Projects to proceed with the construction of the Emerald Way improvements.

 

APPROVED the conversion of the footway/s into a cycle track as set out in Appendix A.

 

AGREED that the Service Director for Strategic Transport and Infrastructure is delegated to approve contractual commitments of up to the value of the released budget of £1,398,400 to deliver the Emerald Way Improvements project

Wards Affected: Aylesbury North West; Aylesbury West;

Contact: Ian McGowan, Head of Highways Infrastructure Projects Email: Ian.McGowan@buckinghamshire.gov.uk.

Publication date: 27/04/2022

Date of decision: 27/04/2022

Effective from: 04/05/2022

Accompanying Documents: