28/01/2020 - Spend Protocol - High Wycombe New Cemetery

This report seeks the consent of the Shadow Executive to proceed with the Penn Road cemetery project, as described in Appendix 1 – Report to Wycombe District Council’s Cabinet of 3rd February 2020.

 

RESOLVED: 

1. That the Shadow Executive notes the content of this report.

2. That the Shadow Executive:

(a) Consents to a project budget increase of £253,210.

(b) Consents to the release other project funds of £389,790.

(c) Consents to the grant of delegated authority to enter into a build contract for the project.

(d) Consents that the £50,000 annual maintenance cost of the new facility will be will be contained within the Special Expenses Reserve (SER) precept.

3. Notes that this matter is also being reported to Wycombe District Council’s Cabinet on February 3rd 2020.