19/03/2021 - South East Aylesbury Link Road Phase 2

The Leader AGREED:

 

To provide delegated authority to the Head of Highways Infrastructure Projects, or appropriate officer, to proceed with the South East Aylesbury Link Road Phase 2:

 

·       prepare and submit a planning application for the dual carriageway and the roundabout link to the South West Aylesbury Link Road,

·       proceed with the detailed design of the dual carriageway and the roundabout link to the South West Aylesbury Link Road,

 

To provide delegated authority to the Director of Property, or appropriate officer, to:

 

·       progress land negotiations for the South East Aylesbury Link Road Phase 2,

 

 To note the main outcomes of the recent public consultation and the project’s response to these.


11/03/2021 - South East Aylesbury Link Road Phase 2 (Decision to be taken)

Recommendations:   

 

To provide delegated authority to the Head of Highways Infrastructure Projects, or appropriate officer, to proceed with the South East Aylesbury Link Road Phase 2:

 

·       prepare and submit a planning application for the dual carriageway and the roundabout link to the South West Aylesbury Link Road,

·       proceed with the detailed design of the dual carriageway and the roundabout link to the South West Aylesbury Link Road,

 

To provide delegated authority to the Director of Property, or appropriate officer, to:

 

·       progress land negotiations for the South East Aylesbury Link Road Phase 2,

 

To note the main outcomes of the recent public consultation and the project’s response to these.