Issue - decisions

27/04/2022 - Emerald Way Improvements Scheme

The Leader:

 

NOTED the results of the public consultation.

 

AGREED to delegate authority to the Head of Highways Infrastructure Projects to complete detailed design following public feedback.

 

AGREED to delegate authority to the Head of Highways Infrastructure Projects to proceed with the construction of the Emerald Way improvements.

 

APPROVED the conversion of the footway/s into a cycle track as set out in Appendix A.

 

AGREED that the Service Director for Strategic Transport and Infrastructure is delegated to approve contractual commitments of up to the value of the released budget of £1,398,400 to deliver the Emerald Way Improvements project


13/04/2022 - Emerald Way Improvements Scheme (Decision to be taken)

Recommendations:

 

That the Leader notes the results of the public consultation.

 

That the Leader delegates authority to the Head of Highways Infrastructure Projects to complete detailed design following public feedback.

 

That the Leader delegates authority to the Head of Highways Infrastructure Projects to proceed with the construction of the Emerald Way improvements.

 

That the Leader approves the conversion of the footway/s into a cycle track as set out in Appendix A.

 

That the Service Director for Strategic Transport and Infrastructure is delegated to approve contractual commitments of up to the value of the released budget of £1,398,400 to deliver the Emerald Way Improvements project